RENCANA ANGGARAN BIAYA ( RAB ) | |||||
PROYEK : Renovasi Rumah Bpk Lutfi/Ibu Millia | |||||
LOKASI : Tangerang dekat bandara | |||||
LUAS BANGUNAN : 124m2 | |||||
NO | URAIAN PEKERJAAN | SAT | VOLUME | HARGA | JUMLAH |
SAT | |||||
I | PEKERJAAN PERSIAPAN | ||||
1 | Pembersihan lapangan | ls | 0,00 | 500.000 | 0 |
2 | Alat kerja | ls | 1,00 | 300.000 | 300.000 |
3 | Keamanan | ls | 1,00 | 350.000 | 350.000 |
3 | Pasang bouplank | m' | 36,00 | 6.000 | 216.000 |
4 | Buat bedeng kerja/ sewa tempat | ls | 0,00 | 2.500.000 | 0 |
Sub total | 866.000 | ||||
II | PEKERJAAN TANAH | ||||
1 | Galian tanah pondasi | m3 | 20,40 | 25.000 | 510.000 |
2 | Urug tanah kembali | m3 | 9,08 | 12.500 | 113.438 |
3 | Urug tanah lantai | m3 | 13,20 | 12.500 | 165.000 |
Sub total | 788.438 | ||||
III | PEKERJAAN PONDASI | ||||
1 | Pasang pondasi batu kali | m3 | 10,73 | 250.000 | 2.681.250 |
2 | Urug pasir bawah pondasi | m3 | 4,29 | 140.000 | 600.600 |
3 | Urug pasir bawah lantai | m3 | 1,18 | 140.000 | 165.060 |
4 | cor cakar ayam | m3 | 0,60 | 3.000.000 | 1.800.000 |
Sub total | 5.246.910 | ||||
IV | PEKERJAAN STRUKTUR | ||||
1 | Cor sloof 20 x 25 | m3 | 2,15 | 3.000.000 | 6.435.000 |
2 | Cor lantai kerja | m2 | 72,00 | 15.000 | 1.080.000 |
3 | Cor kolom 15 x 25 | m3 | 1,05 | 3.000.000 | 3.150.000 |
4 | Cor kolom praktis 15 x 15 | m3 | 3,15 | 3.000.000 | 9.450.000 |
5 | Cor balok 20 x 25 | m3 | 1,80 | 3.000.000 | 5.400.000 |
6 | Cor dak keraton | m2 | 62,00 | 145.000 | 8.990.000 |
7 | Cor ring balok atap | m3 | 1,72 | 3.000.000 | 5.160.000 |
8 | cor meja dapur | m3 | 0,00 | 3.000.000 | 0 |
39.665.000 | |||||
V | PEKERJAAN DINDING LANTAI I | ||||
1 | Pasang batako dinding | m2 | 163,40 | 40.000 | 6.536.000 |
2 | Pasang dinding gypsum | m2 | 25,60 | 65.000 | 1.664.000 |
3 | Plester + aci | m2 | 277,78 | 25.000 | 6.944.500 |
Sub total | 15.144.500 | ||||
VI | PEKERJAAN DINDING LANTAI II | ||||
1 | Pasang batako dinding | m2 | 159,00 | 40.000 | 6.360.000 |
2 | Plester + aci | m2 | 47,70 | 25.000 | 1.192.500 |
Sub total | 7.552.500 | ||||
VII | PEKERJAAN ATAP | ||||
1 | Pasang rangka atap baja ringan | m2 | 72,00 | 70.000 | 5.040.000 |
2 | Pasang penutup atap genteng | m2 | 72,00 | 45.000 | 3.240.000 |
Sub total | 8.280.000 | ||||
VIII | PEKERJAAN KUSEN PINTU & JENDELA | ||||
1 | TIPE P1 (1) | ||||
> Kusen kayu | m1 | 34,30 | 50.000 | 1.715.000 | |
> Pintu Dobel multiplek | unit | 7,00 | 450.000 | 3.150.000 | |
> Handel pintu | unit | 7,00 | 50.000 | 350.000 | |
> kunci pintu | bh | 7,00 | 50.000 | 350.000 | |
> Engsel pintu 4" | bh | 14,00 | 15.000 | 210.000 | |
2 | TIPE P2 | ||||
> Pintu PVC | unit | 5,00 | 180.000 | 900.000 | |
3 | TIPE J1 | ||||
> Kusen kayu | m1 | 21,60 | 50.000 | 1.080.000 | |
> jendela kaca | unit | 6,00 | 450.000 | 2.700.000 | |
> engsel Jendela 3" | bh | 12,00 | 15.000 | 180.000 | |
> Hak angin | bh | 6,00 | 15.000 | 90.000 | |
> Kunci jendela | bh | 6,00 | 15.000 | 90.000 | |
Sub total | 10.815.000 | ||||
IX | PEKERJAAN LANTAI 1 | ||||
1 | Pasang keramik lantai 30X30 | m2 | 41,00 | 50.000 | 2.050.000 |
3 | Pasang lantai teras 30x30 | m2 | 2,57 | 50.000 | 128.500 |
5 | Pasang keramik lantai KM/WC | m2 | 8,00 | 55.000 | 440.000 |
6 | Pasang Keramik dinding | m2 | 28,00 | 55.000 | 1.540.000 |
Sub total | 4.158.500 | ||||
X | PEKERJAAN PENGECATAN | ||||
1 | Cat dinding exterior | m2 | 108,80 | 18.000 | 1.958.400 |
2 | Cat dinding interior | m2 | 236,40 | 15.000 | 3.546.000 |
3 | Cat kusen, pintu dan jendela | ls | 1,00 | 650.000 | 650.000 |
Sub total | 6.154.400 | ||||
XI | PEKERJAAN INSTALASI AIR KOTOR , | ||||
AIR BERSIH & SANITASI | |||||
1 | pasang kloset Jongkok | bh | 5,00 | 150.000 | 750.000 |
3 | pasang kitchen zink | bh | 1,00 | 250.000 | 250.000 |
4 | Pasang kran dinding | bh | 7,00 | 25.000 | 175.000 |
5 | pasang kran dapur | bh | 1,00 | 75.000 | 75.000 |
6 | Pasang instalasi air kotor 4" | m' | 17,00 | 27.500 | 467.500 |
7 | Pasang instalasi air bekas 3" | m' | 17,00 | 27.500 | 467.500 |
8 | Pasang instalasi air bersih 3/4" & 1/2" | m' | 19,00 | 12.500 | 237.500 |
9 | Pasang foldrain | bh | 7,00 | 40.000 | 280.000 |
10 | Pasang bak kontrol | bh | 1,00 | 125.000 | 125.000 |
Sub total | 2.827.500 | ||||
XII | PEKERJAAN INSTALASI LISTRIK | ||||
1 | Instalasi stop kontak | ttk | 6,00 | 50.000 | 300.000 |
2 | Instalasi lampu | ttk | 15,00 | 50.000 | 750.000 |
3 | Panel box MCB 8 Groop | bh | 1,00 | 200.000 | 200.000 |
4 | Kabel toevor | m' | 8,50 | 30.000 | 255.000 |
5 | Pasang stop kontak | bh | 6,00 | 35.000 | 210.000 |
6 | Pasang saklar tunggal | bh | 10,00 | 15.000 | 150.000 |
7 | Pasang saklar dobel | bh | 3,00 | 17.500 | 52.500 |
8 | Kabel arde + pipa 1/2" | ls | 1,00 | 175.000 | 175.000 |
Sub total | 2.092.500 | ||||
XIII | PEKERJAAN LAIN - LAIN | ||||
1 | upah tenaga bor air | ls | 1.300.000 | 1.300.000 | |
2 | Biaya material utk bor air | ls | 1.383.000 | 1.383.000 | |
3 | upah borongan kerja bangunan | m2 | 123,00 | 350.000 | 43.050.000 |
Sub total | 45.733.000 | ||||
TOTAL | 125.899.748 | ||||
1 | cost and fee 13% | 16.366.967 | |||
TOTAL | 142.266.715 | ||||
harga permeter persegi | 2.294.624 |
Rumah-Strategis.com
DESIGN & BUILD
INTERIOR DECORATION
RENOVATION
FURNITURE
ARCHITECH CONSULTANT
DINDING 3D
PARKET
GRATIS !!!
Survey, Desain Layout dan Perhitungan Biaya
FREE BIAYA DESIGN*
*apabila pengerjaan interior dipercayakan kepada kami
GARANSI !!!
Service Gratis Selama 2 Bulan
Taufiq Rahman, ST
(Architect)
Blog.www.tfqarchitects.blogspot.com
Office :Jl.ARS.Muhammad no 2 RT 29 klandasan ulu balikpapan kota
telp/wa : 0812 1880 45 12
Email. tfqabufaris@gmail.com
Ym. Taufiq_archits
Pin BB. 293FE543
CARA MUDAH MENGHITUNG RAB, murah..hanya Rp. 50.000,-
ingin mendapatkan software Menghitung RAB klik disini
ps. Anda bisa memiliki penghasilan sedikitnya 15 Juta Setiap Minggunya Dan Langsung Masuk Ke Rekening Bank BCA Anda. Saya sudah mengalaminya, Anda pun BISA, Asal Tahu ILMU-nya!Download E-booknya hanya disini
DESIGN & BUILD
INTERIOR DECORATION
RENOVATION
FURNITURE
ARCHITECH CONSULTANT
DINDING 3D
PARKET
GRATIS !!!
Survey, Desain Layout dan Perhitungan Biaya
FREE BIAYA DESIGN*
*apabila pengerjaan interior dipercayakan kepada kami
GARANSI !!!
Service Gratis Selama 2 Bulan
Taufiq Rahman, ST
(Architect)
Blog.www.tfqarchitects.blogspot.com
Office :Jl.ARS.Muhammad no 2 RT 29 klandasan ulu balikpapan kota
telp/wa : 0812 1880 45 12
Email. tfqabufaris@gmail.com
Ym. Taufiq_archits
Pin BB. 293FE543
CARA MUDAH MENGHITUNG RAB, murah..hanya Rp. 50.000,-
ingin mendapatkan software Menghitung RAB klik disini
ps. Anda bisa memiliki penghasilan sedikitnya 15 Juta Setiap Minggunya Dan Langsung Masuk Ke Rekening Bank BCA Anda. Saya sudah mengalaminya, Anda pun BISA, Asal Tahu ILMU-nya!Download E-booknya hanya disini
Tidak ada komentar:
Posting Komentar